Foreword
The Central Pollution Control Board plan~ed
nationwide implementation programme of particulate emission standards
in the cement industry after the emission standards for particulate
matter were developed. In the year 1986 the Central Board constituted
a National and four Zonal task Forces with the objective of providing
impetus to pollution control through action-oriented time-bound
programme. Status of implementation of P911ution control measures
and the recommendations of the National Task Force with regard to
follow-up action against the calcitrant units under the provision
of the Air Amended Act, 1987 have been reported in this report.
The National Task Forces held eight meetings since its formation
and also visited a number of cement plants. Due to the persuasion
and pressure built-up by the National and Zonal Task Forces and
the concerned State Boards, out of 94 major. cement plants, 61 have
by now installed the necessary pollution control equipments and
comply with the emission standards and 22 have provided time-bound
programme for meeting emission standards.
|
|